| Building along the embankment
of the river Moika |
|
|
Preparation works, dismantling
of constructions
|
|
completed
|
| Underpinning |
|
90%
|
| Deepening of the basement
|
|
70%
|
| Repair of brick walls, reinforcement
of openings, reinforcement and arrangement of lintels |
|
90%
|
| Repair and reinforcement
of brick arches |
|
100%
|
| Installation of a new reinforced
concrete rib floor |
|
80%
|
| Installation of lantern lights |
|
30%
|
| |
|
|
| Building on Bolshaya Morskaya
street and Palace Square |
|
|
Preparation works, dismantling
of constructions
|
|
completed
|
| Underpinning |
|
90%
|
| Deepening of the basement |
|
25%
|
| Repair of brick walls, reinforcement
of openings, reinforcement and arrangement of lintels |
|
95%
|
| Repair and reinforcement
of brick arches |
|
100%
|
| Installation of a new reinforced
concrete rib floor |
|
70%
|
| Installation of jointless
lantern lights |
|
85%
|
| |
|
|
| Yard No. 4: |
|
|
Works on installation of
translucent coverings have been commenced
Frame works are being mounted. |
|
|
| |
|
|
| Yard No. 5: |
|
25%
|
| Reinforcement of walls for installation of frame works |
|
|
| Removal of stucco from the frontispieces in the yard |
|
50%
|
| |
|
|
| Building No. 5: |
|
|
| Preparation works, dismantling
of constructions |
|
completed
|
| Underpinning |
|
100%
|
Repair of brick walls, reinforcement
of openings, reinforcement and arrangement of lintels
|
|
85%
|
| Repair and reinforcement
of brick arches |
|
90%
|
| Installation of a new reinforced
concrete rib floor |
|
90%
|
| |
|
|
| Building No. 4: |
|
|
| Preparation works, dismantling
of constructions |
|
completed
|
| |
|
|
Building No. 3:
|
|
|
| Preparation works. Dismantling
of constructions |
|
90%
|
| Volume of excavated soil
in the course of basement deepening |
|
3600 Ü3
|
| Concrete volume of solid
constructions |
|
2400 Ü3
|
|
|
|
|
|