Reconstruction and Restoration of the East
Wing of the Former General Staff Building (the State
Hermitage) as of August 25th, 2009.
1.
Construction, Installation and Restoration Works.
From the beginning of contract works the following works
have been practically finished:
|
-
|
|
reinforcement of new openings in brick walls; |
|
-
|
|
installation of monolithic reinforced concrete structures
of skylights; |
|
-
|
|
installation of temporary gas supply; |
|
-
|
|
construction units À¿-1 and ¿-2; rooms are handed
over to Joint Stock Company St Petersburg electrical networks
for mounting of electrical equipment ; |
|
-
|
|
¿-5235 equipment disconnection and dismantling
have been done with transferring the unit to the temporary power
supply diagram; |
In process of implementation:
|
-
|
|
dismantling works; |
|
-
|
|
deepening of basement, damp-proofing, installation
of bored piles; |
|
-
|
|
einforcement of brickwork, including the use of injection
method; |
|
-
|
|
foundations reinforcement; |
|
-
|
|
installation of monolithic reinforced concrete floors; |
|
-
|
|
mounting of the roofing frame (metal constructions
of transparent covers of the 4th courtyard are manufactured and installed,
40 tones of metal structures of floor beams are manufactured
and installed); |
|
-
|
|
manufacturing and mounting of monolithic reinforced
concrete structures of skylights; |
|
-
|
|
preparatory works on decoration and restoration
of rooms (plastering of brick vaults and walls in rooms), preparation
of window fillings and restoration works in workshops outside
the construction site (doors, fireplaces, interior elements); |
|
-
|
|
preparatory works on installation and utilities
arrangement systems (heating, ventilation and conditioning, power
supply, communication and security systems, gas boiler house -
construction readiness); |
|
-
|
|
measures of environmental protection and reduction
of adverse impact on the environment; |
|
-
|
|
monitoring of structures and parts of the building
during execution of works. |
Over a period of January to June, 2009 general contractor
conducted works of the first stage of the project Reconstruction and Restoration
of the East Wing of the Former General Staff Building
(the State Hermitage) to the amount of 1 266 252. 727 rubles.
Payment over the specified period amounts to 1 161 214. 977 rubles
counting in set-off of 105 137.750 rubles from the advance
payment transferred earlier in accordance with the terms of the contract.
2.
During the period from May to August, 2009 manufacturing
and testing of prototypes of constructions of courtyard transparent
cover (glass beam) are conducted for further standardisation and certification
of the construction.
In the course of the glass beam testing at the Central Scientific
Research Institute for Building Structures named after V.A. Koucherenko
the necessity to specify design decisions on the construction and to supplement
the test programme was found. In this connection the preparation
of suggestions on introducing appropriate changes to the schedule
of works for the year 2009 is going on.
3.
Specialists and experts of International Bank for Reconstruction
and Development (IBRD) conducted integrated assessment of the quality
and results of work conducted by the general contractor on implementation
of the first stage of the Contract FC-11(w). On the basis of the results
of this assessment IBRD reconciled continuation of full-scale works
of Limited Liability Company Intarsia on the Contract FC-11(w). The corresponding
additional agreement #1 to the Contract FC-11(w) was
signed on June 29th, 2009.
4.
Questions of the building foundations reinforcement
within the construction site of the second stage of the project have
been considered by specialists of Foundation for Investment Projects
(FISP), of the State Hermitage and of building and design organisations
taking part in implementation of works concerning the first stage
of reconstruction and restoration of the site.