The reconstruction and restoration of the East Wing of
the General Staff Building (State Hermitage Museum) based on its condition
in October 2011.
- Restoration of zones being added to the category of museum items (chapel)
- 10%
- Reinforcing new doorways in the brick walls - 70%
- Construction of in-situ reinforced concrete skylights - 20%
- Construction of partitions - 10%
- Construction of roof covering - 20%
- Placement of window filling - 80%
- Production of window filings at enterprises and restoration at workshops
outside the construction side (doors, fireplaces, interior elements,
including stone) - 50%
- Assembly and installation of internal utility networks (heating, ventilation
and conditioning, electrical power supply, security and communications
systems, roof gas boiler system) - 70%
- Environmental protection measures, reducing negative impact on the
environment - constant
- Monitoring the condition of new construction and the building as a
whole during the process of work - constant
- Construction of in-situ concrete coverings - 80%
- Construction of metal frame gates and movable walls outside the construction
site - 10%
- Construction of in-situ foundation grids, mat and columns of the yards
Nos. 1, 2, 3 - 45%
- In-situ construction of translucent coverings in yards No. 1, 2, 3
- 70%
- Construction of in-situ staircases and elevator shafts - 60%
- Preparatory work on the finishing and restoration of the area (plastering
work on the brick arches and walls) - 80%
- Reinforcing the brickwork using the injection method - 80%
- Assembly of the steel roof construction systems - 40%
- In-situ reinforced concrete construction, units No. 1 and 2 - 80%
Since the beginning of the works the following works were completed:
- Reinforcement of the building's foundation
|